Our Journey

Where it began

The project began with extensive site assessment and feasibility work identifying Dâures Constituency as one of Southern Africa's most technically and economically suited locations for green hydrogen production. An independent Pre-Feasibility Study completed by Fichtner International in April 2024 confirmed the commercial viability of the Phase 2 concept.

Proof of concept

Before scaling to commercial production, the technology was proven on the ground. The Phase 1 and Phase 1.5 pilot plants have been developed at the Dâures site, expected to produce Namibia’s first locally manufactured green fertiliser by the fourth quarter of 2026, generating operational data that will inform the development and optimisation of the commercial-scale project.

Funding for the pilot has been provided by the German Federal Ministry of Education and Research (BMBF), the United Nations Industrial Development Organisation (UNIDO), the United Kingdom Government, and Enersense Energy Namibia, with approximately USD 17.7 million mobilised to date.

Where we are now

The Development Funding Agreement is set for execution on 10 September 2026, formally launching the commercial development phase.

What comes next

Over the next 18 months the project will complete its Engineering studies, environmental assessments, procurement of key technical advisors and secure its financing, working towards a Final Investment Decision in June 2028 and Commercial Operations in March 2030.

Project Timeline

September 2026

Development Funding Agreement signed. Project officially enters commercial development phase.

January 2027

Pre-FEED engineering complete

June 2027

FEED engineering complete.

June 2028

Final Investment Decision.

March 2030

Commercial Operations.